Defects liability period

Updated · Editor: George Vanous (editorial policy)

An artist's rendering of a modern two-story white villa with timber screens, a covered carport with a white sports car and two bicycles, a stone driveway and palm trees under a blue sky
Image: Kayan Villas 2 by IMKAN Properties

The defects liability period is the time after a home is finished during which the developer must repair defects at its own cost. In all three emirates the law sets it at one year for installations (electrical, mechanical, plumbing and drainage) and ten years for structural defects, and no contract can shorten them. Each emirate also has the escrow account keep 5% of the project's money for a year after completion, as a guarantee that defects are put right.

We wrote this so you know your rights once you have the keys; it is not legal advice. The step-by-step guides are What happens at handover in Dubai? and in Abu Dhabi?

The periods, emirate by emirate

Structural Installations Law
Dubai 10 years from the completion certificate 1 year from your handover Law No. 6 of 2019, Article 40
Abu Dhabi 10 years from the completion certificate 1 year from the completion certificate Law No. 3 of 2015, Article 73
Ras Al Khaimah 10 years from completion 1 year from handover Law No. 12 of 2023, Article 49

Ras Al Khaimah has since replaced the 2023 law with Law No. 10 of 2026, in force since September 2026; Al Tamimi & Company and ADG Legal both report that the defect periods and the 5% holdback are unchanged. We have not found its official text yet, so the article numbers above are the 2023 law's.

"Structural" means defects in the structure that threaten the building's safety or durability, or its collapse; "installations" means the building's mechanical, electrical, sanitary and drainage works. Snags you find at handover, such as a scratched floor or a door that sticks, belong on your snagging list before you sign.

When the clock starts

The start date is the trap. In Abu Dhabi both periods run from the Municipality's final completion certificate, not from the day you get the keys, so if handover comes months after completion, part of your year has gone before you move in. In Dubai the one-year period runs from your handover, but Article 40 adds that if you do not take possession, for any reason, it runs from the completion certificate instead: delaying your own handover can shorten it. Ask for the completion certificate's date when you are invited to handover.

The 5% held back

The holdback covers the first year only. For the ten-year structural period, your claim is against the developer itself.

Your other rights

The defects liability period is a floor, not a ceiling. In Dubai, Article 40 says it takes away no right or warranty you have under other laws, and the ten-year liability sits alongside the federal rules on construction contracts. Those rules apply in every emirate: under the UAE's Civil Transactions Law, Federal Decree-Law No. 25 of 2025 (in force since Jun 1, 2026), the contractor and the engineer are jointly liable for ten years from delivery for a collapse or for defects that threaten the building's structural integrity (Article 821), a clause limiting that is void (Article 823), and a claim must be brought within three years of the collapse or of finding the defect (Article 824). Note that last limit: report a structural defect as soon as you see it. In Abu Dhabi, Article 17 of Law No. 3 of 2015 counts a unit proved unusable after delivery because of fundamental construction defects as a fundamental breach, which can let the buyer rescind the sale, and since Law No. 2 of 2025 the Owners' Committee can report structural defects in the common parts to the developer or the Department. Repairing defects is the developer's cost, never a service charge.

What to do

  1. Get the completion certificate's date and diary both deadlines.
  2. Report every defect in writing as soon as you find it, with photos, and keep the developer's reply.
  3. Book an inspection a month or two before the one-year date, so installations are reported while they are still covered.
  4. If the developer does not act, take legal advice: in Dubai, RERA oversees developers; in Abu Dhabi, ADREC; in Ras Al Khaimah, RAK Municipality's Real Estate Regulatory Administration.
  5. On a resale, ask the seller for the completion date and any open defect reports, since the periods run from completion or the first handover, not from your purchase.

More terms

The whole glossary

From the blog

All posts

Buying off-plan in the UAE? Talk to us.