The Beach Collection Frond J handover date

Nakheel estimates construction completion for March 2030, the month its payment plan sets for the final 30%. It is Nakheel's estimate from its price sheet of Nov 23, 2026, not a date in a contract yet.

Checked against the sources below on . Nakheel is the developer; Emigeo Homes Real Estate LLC, which runs Homes.me, is a licensed broker and may be paid a commission by the developer. Prices and dates can change, and nothing here is financial advice.

What is paid by when, up to the handover

WhenDuePaid in total
On booking20%20%
April 20275%25%
August 20275%30%
December 202710%40%
April 20285%45%
August 20285%50%
December 202810%60%
April 20295%65%
August 20295%70%
March 203030%100%

Handover years in Dubai, for comparison

Handover yearProjects in our catalog
2026230
2027330
2028235
2029142
2030, the year of Frond J41
20317
The 985 Dubai projects in our catalog with a handover year from 2026 on, as developers publish them. Catalog as of Nov 1, 2026.

What to know

From the first instalment in April 2027 to completion is 35 months, and the last instalment before it, in August 2029, leaves 7 months with nothing to pay while the villas are finished.

The date that binds Nakheel is the one in the sale agreement, with its clause on delay. At handover the villa comes without a pool or landscaping, which Nakheel leaves to the owner, so allow time and budget for those before moving in.

Sources: Palm Jebel Ali, Nakheel's site for the island (the Frond J price sheet, factsheet, brochure and EOI notice are Nakheel's documents for brokers), read Nov 25, 2026.

Frond J EOI Frond J payment plan Frond J prices Frond J floor plans Frond J brochure Frond J: images and floor plans Register for Frond J

In depth: What happens at handover in Dubai.

More about the Frond J handover date

Has Nakheel given a handover day for Frond J?

No, only a month: March 2030, marked as estimated construction completion.

What do I pay at Frond J's completion?

30% of the price: AED 7,809,000 on a six-bedroom at its starting price.

Is Frond J finished before Palm Central Frond D?

On the two estimates, yes: Nakheel gives March 2030 for Frond J and October 2030 for Palm Central's Frond D release.

Ask us about The Beach Collection Frond J

Planning around a 2030 move, or a sale before completion? Leave a number and an advisor calls you back.

Call me back

An advisor in Dubai replies on WhatsApp or calls within 15 minutes during working hours. No spam, no call centre. Privacy