Look the project up on the Dubai Land Department's (DLD) Project Status Enquiry, which shows its developer, how far it is built and the bank that holds its escrow account. Then make sure every payment goes into that project's escrow account, check the broker's card on the DLD's e-card verification page, scan the QR code on the advertisement, and after you sign, get the Oqood registration of your purchase. The first four cost nothing and take minutes.
We wrote this from Dubai's escrow law and the DLD's own pages, read on Nov 23, 2026. It is a guide to the questions worth asking, not legal or financial advice, and passing every check does not make a project a good buy or promise that it will finish on time. Confirm anything that matters to your purchase with the DLD or a lawyer.
Why check at all?
Because Dubai's law sets conditions a developer must meet before it may sell you anything off-plan, and you can see most of them for yourself. Law No. 8 of 2007, the law on escrow accounts for real estate development, says:
- The developer must be registered. Article 4 has the DLD keep a Register of Real Estate Developers, and no developer may work in the business unless it is on that register and licensed.
- The project needs an escrow account before sales start. Under Article 6, a developer that wants to sell units off-plan must ask the DLD to open one, with its trade license, the title deed of the land, approved designs and plans, a statement of the project's estimated cost and revenue certified by an auditor, and a standard sale contract.
- Advertising needs written approval. Article 5 bars a developer from advertising off-plan units in the media or at exhibitions without the DLD's written authorization.
- Breaking the rules is a crime. Article 16 sets a jail sentence and a fine of at least AED 100,000, or either, for selling without a license and for knowingly offering units in fraudulent projects, among other offenses.
So a project that cannot pass the checks below has a question to answer before you pay.
Is the project registered with the DLD?
Search for it on the DLD's Project Status Enquiry, by project name or number. It is also in the DLD's Dubai REST app, where the service is called Mashrooi. A project's entry includes:
| Section | Shows |
|---|---|
| Project details | Number, status, % built, units, start and end dates |
| Inspection details | The DLD's inspection records |
| Developer details | The registered developer and its contacts |
| Escrow account | The bank that holds the escrow account |
| Management companies | Who manages the building |
The completion percentage comes from the project's latest approved technical audit, the DLD says in its frequently asked questions, so it shows the last audit rather than today's site. Compare it with what the sales team tells you.
What if you cannot find it? Ask the developer for the project's DLD number and search again. If the developer cannot give you one, do not pay a deposit until it can.
Is your money going into the project's escrow account?
It should go nowhere else. Article 7 of the escrow law has buyers' payments deposited in an account opened in the name of the project, and Article 9 dedicates that account to building that one project, keeps the developer's creditors from attaching it and requires a separate account for each project.
- Find the escrow bank on the project's DLD entry.
- Check that the account in your sale and purchase agreement and on every payment request is at that bank and in the project's name.
- Pay by bank transfer or cheque to that account, never in cash and never to a person, a broker or another company.
- Keep every receipt. Article 12 gives depositors the right to see their own records in the account and to ask for copies.
The law makes no exception for a booking deposit: Article 7 covers the payments off-plan buyers make, so if you are asked to pay one anywhere else, ask why in writing. How much is the down payment on off-plan property in Dubai? covers what developers usually ask for up front.
Is the broker licensed?
Ask for the broker's card number and check it on the DLD's e-card verification page: choose the card type (a broker card), enter the number, and the record comes up, or nothing does. The DLD's frequently asked questions say a broker must be registered in the brokers registry and hold a broker card from the Real Estate Regulatory Agency (RERA), and that the card is valid only as long as the office's license.
This protects the developer's side too: Article 16 of the escrow law makes it an offense for a developer to deal with a broker who is not on the DLD's register.
Is the advertisement approved?
Look for a QR code. Since Apr 24, 2023, every real estate company in Dubai has had to put a QR code from the DLD's Madmoun service on its print and audiovisual ads, the DLD announced on Apr 18, 2023. Scanning it shows that RERA approved the ad, who placed it and the property's details, and whether it has been sold or rented. The DLD advises buyers to deal only with ads that carry the code.
The code comes with an advertising permit from the DLD's Trakheesi system. The permit's service page covers ads in newspapers, by SMS, online and on billboards, open house events and project launches, and adds one rule for exhibitions that is worth knowing: Dubai off-plan properties that are not registered with the DLD's Escrow Account Department may not be shown at them.
What should happen after you sign?
Your purchase is entered in the Interim Real Estate Register, a step called Oqood. It is not a formality: Article 3 of Law No. 13 of 2008 says a sale of an off-plan unit that is not entered in that register is void. The DLD's service page for the registration sends the result to the buyer by email, so ask for it and keep it. The fee is 4% of the price; Can foreigners buy off-plan property in Dubai? sets out who pays what.
What if the project is canceled?
The money in escrow is there to be returned. The DLD's frequently asked questions say that when a project is canceled, its account passes to the DLD's project liquidation department, which asks the developer to refund buyers within 60 days of the cancellation decision (a period RERA can extend), and refers the matter to court if the developer does not pay. While a project is only stalled and not canceled, the DLD cannot end your contract for you: a buyer who wants out has to go to court, and the DLD's role is to try to settle the dispute. What if you miss off-plan payments in Dubai? covers the other side, when a buyer stops paying.
The checks in one list
| Check | What you want to see |
|---|---|
| Project status | The project, your developer, an escrow bank |
| Your contract | Payments only to the project's own account |
| Broker card | A valid card |
| Madmoun QR code | An approved ad that matches the offer |
| Oqood email | Your unit in the Interim Register |
If any check fails, stop and ask the DLD before you pay; its call center is on 8004488.
Every Dubai project in our catalog has its own page with the developer, payment plan and handover date it publishes; browse them from our Dubai guide, work out the full cost of a purchase with the calculators on our tools page, or ask the advisor to narrow the list by budget and handover. Then run the five checks above on the one you like.