What if you miss off-plan payments in Abu Dhabi?

An artist's rendering at sunrise of two curved, terraced apartment buildings on Saadiyat, with palm trees, flower beds and a crossing in front
Image: Mamsha Gardens by Aldar Properties

The developer must first give you 60 days' written notice to pay what is overdue, and the authorities invite you both to settle before those 60 days end. If you still have not paid or settled, the developer may cancel your purchase without going to court, resell the unit and keep between 10% and 40% of the contract value from what you paid into escrow, depending on how far the project is built. The rest comes back to you within 15 working days of asking. These rules are in Article 17(3) of Abu Dhabi's Law No. 3 of 2015, as replaced by Law No. 2 of 2025, and in Administrative Decision No. 165 of 2025, which sets the percentages. ADREC, the emirate's real estate regulator, publishes all three on its regulations page.

This is a summary to help you understand the rules before you sign, not legal, tax or financial advice. If you are behind on payments, talk to the developer and to a lawyer.

Which rules apply?

Off-plan sales in Abu Dhabi are governed by Law No. 3 of 2015 on regulating the real estate sector. Its original Article 17 let either the developer or the buyer rescind an off-plan contract for a substantial breach, after first asking the other side to put it right. It set no scale for what a developer could keep.

That changed in two steps:

Rule Sets
Law No. 2 of 2025 Cancelling without a court
Administrative Decision No. 165 of 2025 What a developer may keep

Law No. 2 of 2025 replaced Article 17(3) with a set procedure that lets a developer cancel without going to court or arbitration, and took effect 90 days after it was published in the Official Gazette. Decision No. 165 sets the share a developer may keep, by construction progress, and the deadlines for refunds, and took effect when it was published. The Department of Municipalities and Transport (DMT) announced Decision No. 165 on Mar 27, 2026, with three other decisions on escrow, jointly owned property and owners' committees. Every rule below comes from those texts unless another source is named.

What happens first when you miss a payment?

The law sets out the steps, in order:

  1. The developer sends you a notice through a notary public or by registered mail, at the address in your purchase contract, asking you to pay what is overdue within 60 days. If your purchase is mortgaged, your bank gets the same notice.
  2. After 15 days, the developer tells the authorities, with proof that you were notified and a certificate from the escrow account's trustee bank stating that you are in breach.
  3. You are invited to settle. On its own initiative, or when you, the developer or your bank asks, the authority invites you both to an amicable settlement before the 60 days run out. A settlement is written up as an annex to your contract.
  4. If there is no settlement, or you do not meet it in the time given, the developer may terminate the contract.

Keep your address up to date with the developer, because the notice goes to the one in your contract.

What happens after the developer cancels?

The developer asks for the cancellation, and the authorities act on it:

How much can the developer keep?

It depends on how far the project's construction works have gone, as certified by ADREC when the developer asks to cancel. The percentage is of the value of the sale contract, taken from what you paid into the escrow account, and any excess is refunded to you.

Project built Developer may keep
Not started, not the developer's fault Nothing: all you paid comes back
Started, below 10% 10% of the price
Above 10%, up to 30% 15% of the price
Above 30%, up to 60% 25% of the price
Above 60%, up to 100% 40% of the price

Three things in that table are easy to misread:

How fast do you get your money back?

Under Article 4 of Decision No. 165, the escrow bank pays:

If the developer took any money from you outside the escrow account, which the law forbids, it must refund all of it within 30 days of ADREC's letter, before anything is refunded to you from escrow.

Can you still go to court?

Yes. Article 17(3) says these rules do not take away a buyer's right to go to court or arbitration if the buyer considers it necessary.

How is this different from Dubai?

Both emirates now let a developer cancel without a court, on a scale tied to construction. The details differ:

Abu Dhabi Dubai
Notice to pay 60 days, from the developer 30 days, from the DLD
Most kept 40%, above 60% built 40%, from 60% built
Refund due 15 working days after you ask 1 year, or 60 days after resale

Our post What if you miss off-plan payments in Dubai? walks through Dubai's rules in full.

How do you avoid getting here?

  1. Read the payment plan as dates and amounts, not percentages, and check you can meet each one if your income dips. Our payment plan calculator turns a plan like "20 / 30 / 50" into a schedule.
  2. Look at what is due before handover. A plan that leaves part of the price until after you get the keys spreads the load: 5 of the 59 Abu Dhabi projects in our catalog, as imported on Nov 1, 2026, offer a post-handover plan, and the advisor can find them for you.
  3. If you plan to borrow, know the limit first. Banks may lend at most half of an off-plan home's value, as our post Can you mortgage off-plan property in Abu Dhabi? explains.
  4. Pay only into the project's escrow account and keep every receipt. Money paid there is what the refund rules protect.
  5. Answer a notice at once, and ask for a settlement within the 60 days rather than after them.
  6. Have a lawyer read the contract, including its own default clauses, before you sign.